<?xml-stylesheet type="text/xsl" media="screen" href="/~d/styles/rss2full.xsl"?><?xml-stylesheet type="text/css" media="screen" href="http://feeds.feedburner.com/~d/styles/itemcontent.css"?><rss xmlns:content="http://purl.org/rss/1.0/modules/content/" xmlns:wfw="http://wellformedweb.org/CommentAPI/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:atom="http://www.w3.org/2005/Atom" xmlns:sy="http://purl.org/rss/1.0/modules/syndication/" xmlns:slash="http://purl.org/rss/1.0/modules/slash/" xmlns:feedburner="http://rssnamespace.org/feedburner/ext/1.0" version="2.0">

<channel>
	<title>Cesar E. Chavez Memorial Building Modernization</title>
	
	<link>http://www.chavezmodernization.com</link>
	<description />
	<lastBuildDate>Fri, 25 May 2012 14:29:38 +0000</lastBuildDate>
	<language>en</language>
	<sy:updatePeriod>hourly</sy:updatePeriod>
	<sy:updateFrequency>1</sy:updateFrequency>
	<generator>http://wordpress.org/?v=3.1.1</generator>
		<atom10:link xmlns:atom10="http://www.w3.org/2005/Atom" rel="self" type="application/rss+xml" href="http://feeds.feedburner.com/ChavezModernization" /><feedburner:info uri="chavezmodernization" /><atom10:link xmlns:atom10="http://www.w3.org/2005/Atom" rel="hub" href="http://pubsubhubbub.appspot.com/" /><feedburner:emailServiceId>ChavezModernization</feedburner:emailServiceId><feedburner:feedburnerHostname>http://feedburner.google.com</feedburner:feedburnerHostname><item>
		<title>Friday May 25 Project Update</title>
		<link>http://feedproxy.google.com/~r/ChavezModernization/~3/6cN_croDF9s/</link>
		<comments>http://www.chavezmodernization.com/2012/05/25/friday-may-25-project-update/#comments</comments>
		<pubDate>Fri, 25 May 2012 14:29:38 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=891</guid>
		<description><![CDATA[Update of Construction From Last Night: worked on reinforcing the glass walls in the conference rooms on 8 west, worked grid ceiling tile in IT room 6th floor, drop ceiling tile on 8 north, west, and south, damper framing on &#8230; <a href="http://www.chavezmodernization.com/2012/05/25/friday-may-25-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Update of Construction From Last Night:</strong></p>
<ul>
<li>worked on reinforcing the glass walls in the conference rooms on 8 west,</li>
<li>worked grid ceiling tile in IT room 6th floor,</li>
<li>drop ceiling tile on 8 north, west, and south,</li>
<li>damper framing on 6th floor,</li>
<li>tie back drywall on 6th floor,</li>
<li>tape and finish on 6 east,</li>
<li>soffits touch up on 9,</li>
<li>finish bulk heads on 9 east,</li>
<li>rework touch up on 8 south diagonal,</li>
<li>worked on testing flows and tampers on 6,7,8,9,</li>
<li>sprinkler heads on 9 east,</li>
<li>FLS upgrades on 6th floor.</li>
<li>worked on fire damper install on 6th floor,</li>
<li>slots on 8 north west,</li>
<li>seal existing duct in 6th SE room</li>
<li>worked on duct replacement on 6 east.</li>
<li>worked on dust and clean throughout.</li>
<li>worked on lights on 3 east,</li>
<li>fire damper power and fire alarm on 3rdf floor,</li>
<li>HVAC power on 3 east.</li>
<li>assisted in testing flows and tampers on 6,7,8,9,</li>
<li>worked lobby wall stone demo on first floor,</li>
<li>lobby floor stone demo on 2nd floor.</li>
<li>worked on stool sill touch up punch on 8 south, 7 south</li>
<li>worked on controls 9th floor,</li>
</ul>
<img src="http://feeds.feedburner.com/~r/ChavezModernization/~4/6cN_croDF9s" height="1" width="1"/>]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/25/friday-may-25-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		<feedburner:origLink>http://www.chavezmodernization.com/2012/05/25/friday-may-25-project-update/?utm_source=rss&amp;utm_medium=rss&amp;utm_campaign=friday-may-25-project-update</feedburner:origLink></item>
		<item>
		<title>Thursday May 24 Project Update</title>
		<link>http://feedproxy.google.com/~r/ChavezModernization/~3/QWsTVwjevXc/</link>
		<comments>http://www.chavezmodernization.com/2012/05/24/thursday-may-24-project-update/#comments</comments>
		<pubDate>Thu, 24 May 2012 13:53:03 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=888</guid>
		<description><![CDATA[Upcoming Tenant Move: 8th Floor South Furniture set up: Wed May 30 30 at 6:00 pm Tenant Move: Friday June 1: at 6:00 am Update of Construction From Last Night: worked on chair rail touch up on 3 west , &#8230; <a href="http://www.chavezmodernization.com/2012/05/24/thursday-may-24-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Upcoming Tenant Move: 8th Floor South</strong></p>
<ul>
<li>Furniture set up: Wed May 30 30 at 6:00 pm</li>
<li>Tenant Move: Friday June 1: at 6:00 am</li>
</ul>
<p><strong>Update of Construction From Last Night:</strong></p>
<ul>
<li>worked on chair rail touch up on 3 west ,</li>
<li>top of wall track repair and re-set on 8th floor east (Tomorrow night we will reinforce the walls at the glass doors on 8 west).</li>
<li>Noisy FPVAV box on 3rd floor West is being investigated.</li>
<li>T.V. recep was installed in office on 9th floor north west.</li>
<li>worked grid on ceiling tile drop in S.S.A.IT room,</li>
<li>ceiling tile in OIG</li>
<li>sanded 7th floor east (ready for first coats of paint),</li>
<li>6th floor east touch up,</li>
<li>9th floor east touch up,</li>
<li>damper framing on 6th floor elevator lobby</li>
<li>dropped ceiling tiles on 8thfloor west and south,</li>
<li>worked on valve replacements on 6th floor,</li>
<li>move line on 9 east,</li>
<li>worked on fire damper install on 6th floor,</li>
<li>Repair damaged duct from damper replacement in restrooms,</li>
<li>layout slot diffusers on 9 north east,</li>
<li>worked on 6th floor duct replacement to boxes 6-2, 6-1, 6-3, 9th floor north east corner.</li>
<li>employees worked on dust and clean throughout.</li>
<li>3 east lighting,</li>
<li>6 south lighting,</li>
<li>outlet install in office 9th floor north west corner for T.V.</li>
<li>demo of old soffit tie in at framing 2ndfloor east,</li>
<li>7th floor east ceiling demo.</li>
<li>worked on stool sill touch up punch on 8 south, 8 west, 3 west.</li>
<li> </li>
</ul>
<img src="http://feeds.feedburner.com/~r/ChavezModernization/~4/QWsTVwjevXc" height="1" width="1"/>]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/24/thursday-may-24-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		<feedburner:origLink>http://www.chavezmodernization.com/2012/05/24/thursday-may-24-project-update/?utm_source=rss&amp;utm_medium=rss&amp;utm_campaign=thursday-may-24-project-update</feedburner:origLink></item>
		<item>
		<title>Wednesday May 23 Project Update</title>
		<link>http://feedproxy.google.com/~r/ChavezModernization/~3/pdQetNAOi1I/</link>
		<comments>http://www.chavezmodernization.com/2012/05/23/wednesday-may-23-project-update/#comments</comments>
		<pubDate>Wed, 23 May 2012 13:58:42 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=885</guid>
		<description><![CDATA[4 week Look-a-Head Schedule: Tenant Relocation Schedule: Update of Construction from Last Night: S.S.A. IT room on 6 west was inspected by GEJCC and Jacobs. Tile should be getting dropped by 4:30. DOEd O.I.G. room should get inspected and ceiling &#8230; <a href="http://www.chavezmodernization.com/2012/05/23/wednesday-may-23-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>4 week Look-a-Head Schedule:</strong></p>
<p><strong><a class="downloadlink" href="http://www.chavezmodernization.com/wp-content/plugins/download-monitor/download.php?id=132" title=" downloaded 2 times" >4 week look-a-head schedule May 21 (2)</a></strong></p>
<p><strong>Tenant Relocation Schedule:</strong></p>
<p><strong><a class="downloadlink" href="http://www.chavezmodernization.com/wp-content/plugins/download-monitor/download.php?id=131" title=" downloaded 2 times" >Tenant Relocation Schedule May 21 (2)</a></strong></p>
<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>S.S.A. IT room on 6 west was inspected by GEJCC and Jacobs. Tile should be getting dropped by 4:30.</li>
<li>DOEd O.I.G. room should get inspected and ceiling dropped tomorrow</li>
<li>worked on barrier removal on 2 east</li>
<li>worked on ceiling wires on 7 west,</li>
<li>framing on north east corner at the stair way,</li>
<li>tape and finish touch up on 9 and 8 east,</li>
<li>drywall repairs in day care infant room,</li>
<li>tape and finish on 6 and 7 east,</li>
<li>6th floor damper framing.</li>
<li>worked S.S.A. fire sprinkler in secure room,</li>
<li>heads on 3 east, life safety upgrades on the north elevation</li>
<li>worked on fire damper install on 6th floor,</li>
<li>8 south punch list</li>
<li>worked on duct replacement and install on 6th floor east</li>
<li>worked on dust and clean throughout building</li>
<li>lights on 6thfloor, lights on 3 east,</li>
<li>worked on ceiling demo on 6 east,7th floor ceiling demo</li>
<li>worked on stool sill touch up on 8 south, 8 west, 3 west.</li>
<li>worked on carpet on 9 east</li>
</ul>
<img src="http://feeds.feedburner.com/~r/ChavezModernization/~4/pdQetNAOi1I" height="1" width="1"/>]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/23/wednesday-may-23-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		<feedburner:origLink>http://www.chavezmodernization.com/2012/05/23/wednesday-may-23-project-update/?utm_source=rss&amp;utm_medium=rss&amp;utm_campaign=wednesday-may-23-project-update</feedburner:origLink></item>
		<item>
		<title>Tuesday May 22 Project Update</title>
		<link>http://feedproxy.google.com/~r/ChavezModernization/~3/pwDU_khPHNo/</link>
		<comments>http://www.chavezmodernization.com/2012/05/22/tuesday-may-22-project-update/#comments</comments>
		<pubDate>Tue, 22 May 2012 13:52:36 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=881</guid>
		<description><![CDATA[Upcoming Electrical Outage Friday June 1 Time: 7:00 pm Friday until 5:30 am Saturday Morning Floors: 6, 7, and 8 Update of Construction From Last Night: worked on barrier removal prep on 2 east worked grid on the grid in &#8230; <a href="http://www.chavezmodernization.com/2012/05/22/tuesday-may-22-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Upcoming Electrical Outage Friday June 1</strong></p>
<ul>
<li>Time: 7:00 pm Friday until 5:30 am Saturday Morning</li>
<li>Floors: 6, 7, and 8</li>
</ul>
<p><strong>Update of Construction From Last Night:</strong></p>
<ul>
<li>worked on barrier removal prep on 2 east</li>
<li>worked grid on the grid in S.S.A. on 6th floor East (Ready for lights and sprinklers),</li>
<li>grid on 9 east,</li>
<li>tie backs drywall on 6 east,</li>
<li>framing at north east corner behind stairs level 9 and 3,</li>
<li>tape and finish on 8,7,6 east</li>
<li>worked on fixing leaky head on 8th floor east,</li>
<li>heads dropped in 3 east,</li>
<li>Fire life Safety upgrades heads on 6 north,</li>
<li>worked on fire damper install on 3rd floor,</li>
<li>worked on duct replacement on 8th floor east,</li>
<li>measure duct on 7 east</li>
<li>worked on dust and clean throughout,</li>
<li>final clean on 9 south and 3 south.</li>
<li>3rd floor east fire alarm rough,</li>
<li>HVAC power on 6 east,</li>
<li>worked on fire alarm trim out on 6 south</li>
<li>ceiling demo on 6 east,</li>
<li>2nd floor wall stone demo,</li>
<li>worked on stool sill touch up on pre-punch on 7,</li>
<li>punch list on 3 south,</li>
<li>touch up on 8 south,</li>
<li>prep on 7 south</li>
<li>&#8211;</li>
</ul>
<img src="http://feeds.feedburner.com/~r/ChavezModernization/~4/pwDU_khPHNo" height="1" width="1"/>]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/22/tuesday-may-22-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		<feedburner:origLink>http://www.chavezmodernization.com/2012/05/22/tuesday-may-22-project-update/?utm_source=rss&amp;utm_medium=rss&amp;utm_campaign=tuesday-may-22-project-update</feedburner:origLink></item>
		<item>
		<title>Exit Door Closure: Alley Side</title>
		<link>http://feedproxy.google.com/~r/ChavezModernization/~3/UlVxy6dt13s/</link>
		<comments>http://www.chavezmodernization.com/2012/05/21/exit-door-closure-alley-side/#comments</comments>
		<pubDate>Mon, 21 May 2012 14:38:28 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=878</guid>
		<description><![CDATA[﻿﻿Back Door Closure: Starts Today May 21 Duration: 6 Weeks Closure Location: Single Door exiting to Alley. (Hallway just south of Main Entrance, by Janitorial room) Work: Installation of new exterior skin by double doors near trash area in the &#8230; <a href="http://www.chavezmodernization.com/2012/05/21/exit-door-closure-alley-side/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p>﻿﻿<strong>Back Door Closure: Starts Today May 21</strong></p>
<ul>
<li>Duration: 6 Weeks</li>
<li>Closure Location: Single Door exiting to Alley. (Hallway just south of Main Entrance, by Janitorial room)</li>
<li>Work: Installation of new exterior skin by double doors near trash area in the alley.</li>
</ul>
<img src="http://feeds.feedburner.com/~r/ChavezModernization/~4/UlVxy6dt13s" height="1" width="1"/>]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/21/exit-door-closure-alley-side/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		<feedburner:origLink>http://www.chavezmodernization.com/2012/05/21/exit-door-closure-alley-side/?utm_source=rss&amp;utm_medium=rss&amp;utm_campaign=exit-door-closure-alley-side</feedburner:origLink></item>
		<item>
		<title>Thursday May 17 Project Update</title>
		<link>http://feedproxy.google.com/~r/ChavezModernization/~3/So9bNs3GoAY/</link>
		<comments>http://www.chavezmodernization.com/2012/05/17/thursday-may-17-project-update/#comments</comments>
		<pubDate>Thu, 17 May 2012 13:48:50 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=874</guid>
		<description><![CDATA[Possible Smells: Today: Paint: 8 south final coats, primed walls on 7 south Welding in the new lobby on the ceiling of the 2nd floor during the day. Painting: 7th floor Friday:Welding in the lobby from 5:00 pm to 3:30 &#8230; <a href="http://www.chavezmodernization.com/2012/05/17/thursday-may-17-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Possible Smells:</strong></p>
<ul>
<li>Today: Paint: 8 south final coats, primed walls on 7 south</li>
<li>Welding in the new lobby on the ceiling of the 2nd floor during the day.</li>
<li>Painting: 7th floor</li>
<li>Friday:Welding in the lobby from 5:00 pm to 3:30 am</li>
</ul>
<p><strong>Tenant Relocation:</strong></p>
<ul>
<li>9th and 3rd Floor South: Wednesday May 23 at 9:30 am</li>
</ul>
<p><strong>Update of Construction From Last Night:</strong></p>
<ul>
<li>worked on removal of barriers on the north east corner of the building.</li>
<li>worked on 9th floor east tie back framing and door frame install, tape and finish on 8,7,6 east, framing of damper walls on 3rd floor restrooms, drywall 6 east tie backs, grid on 3 east, drywall on 6 east tie backs, grid on first floor.</li>
<li>worked on heads on 7 south, first floor sprinkler lines, heads on 6 south</li>
<li>worked on fire damper install on 3rd floor,</li>
<li>7thfloor west and south GRD’s,</li>
<li>above ceiling punch on 7 west and south, low pressure duct on 1st floor, off set elbows on duct on the 9th floor</li>
<li>worked on duct replacement on 8th floor at boxes 8-5,8-4,8-2, measure for duc ton 6 east</li>
<li>worked on dust and clean throughout</li>
<li>worked on secure room electrical above ceiling 8th floor north,</li>
<li>worked on power for furniture move backs on 3 north,</li>
<li>lighting rough in 3 east,</li>
<li>HVAC power 8 north,</li>
<li>7th floor above ceiling punch list</li>
<li>worked on fire alarm trim and devices on 7 east and elevator lobbies east all floors</li>
<li>worked lobby stone demo on second floor</li>
<li>worked on 8 south final coats, primed walls on 7 south</li>
<li>worked on stool sill touch up on 3 south, 9 south</li>
</ul>
<img src="http://feeds.feedburner.com/~r/ChavezModernization/~4/So9bNs3GoAY" height="1" width="1"/>]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/17/thursday-may-17-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		<feedburner:origLink>http://www.chavezmodernization.com/2012/05/17/thursday-may-17-project-update/?utm_source=rss&amp;utm_medium=rss&amp;utm_campaign=thursday-may-17-project-update</feedburner:origLink></item>
		<item>
		<title>Tuesday May 15 Project Update</title>
		<link>http://feedproxy.google.com/~r/ChavezModernization/~3/0I8Zewt9Zdg/</link>
		<comments>http://www.chavezmodernization.com/2012/05/15/tuesday-may-15-project-update/#comments</comments>
		<pubDate>Tue, 15 May 2012 14:08:48 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=846</guid>
		<description><![CDATA[Update of Construction from Last Night: drywall on 6 east, drywall on 7 east tie backs, started grid on first floor fitness, tape and finish on 8 east, tape and finish on 7 east, drywall on 6 east, started shooting &#8230; <a href="http://www.chavezmodernization.com/2012/05/15/tuesday-may-15-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>drywall on 6 east,</li>
<li>drywall on 7 east tie backs,</li>
<li>started grid on first floor fitness,</li>
<li>tape and finish on 8 east,</li>
<li>tape and finish on 7 east,</li>
<li>drywall on 6 east,</li>
<li>started shooting wires and installing wall angle on 3 east,</li>
<li>tape and finish on 6 south</li>
<li>worked on 6th floor west and 8 south sprinkler heads.</li>
<li>worked on 8th floor room V.A.V.s and duct,</li>
<li>damper install on 3rd floor,</li>
<li>worked on controls for the 8th floor room V.A.V.s</li>
<li>worked on 8th floor room duct demo and replacement, FPVAV 8-5</li>
<li>worked on dust and clean throughout building and final clean of 6 and 7 west.</li>
<li>worked on disconnects on 9th floor,</li>
<li>6th floor south lighting, fire alarm &amp; power across 9th floor lobby for dampers,</li>
<li>worked on 3rd floor punch,</li>
<li>9th floor south punch, started painting locker room ceiling</li>
</ul>
<img src="http://feeds.feedburner.com/~r/ChavezModernization/~4/0I8Zewt9Zdg" height="1" width="1"/>]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/15/tuesday-may-15-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		<feedburner:origLink>http://www.chavezmodernization.com/2012/05/15/tuesday-may-15-project-update/?utm_source=rss&amp;utm_medium=rss&amp;utm_campaign=tuesday-may-15-project-update</feedburner:origLink></item>
		<item>
		<title>Friday May 11 Project Update</title>
		<link>http://feedproxy.google.com/~r/ChavezModernization/~3/kGapiAR6yjA/</link>
		<comments>http://www.chavezmodernization.com/2012/05/11/friday-may-11-project-update/#comments</comments>
		<pubDate>Fri, 11 May 2012 13:45:02 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=844</guid>
		<description><![CDATA[Update of Construction from Last Night: worked on pre-punch list for tomorrow’s 3rd floor south walk, pre-punch on 9 south, punch items from 7th and 6th west, worked with prestige for furniture move backs. worked on demo for damper replacements, &#8230; <a href="http://www.chavezmodernization.com/2012/05/11/friday-may-11-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>worked on pre-punch list for tomorrow’s 3rd floor south walk,</li>
<li>pre-punch on 9 south,</li>
<li>punch items from 7th and 6th west,</li>
<li>worked with prestige for furniture move backs.</li>
<li>worked on demo for damper replacements,</li>
<li>drywall on 6 east,</li>
<li>drywall on 7 east,</li>
<li>tape and finish on first floor fitness,</li>
<li>sanding on 9 east,</li>
<li>tape and finish on 8 east,</li>
<li>started tape and finish on 7 east,</li>
<li>sanded drywall in judges office on 6 north west for wall paper,</li>
<li>worked on patches and pre-punch on 3 south,</li>
<li>rebuild framing for damper in level 2 men’s room,</li>
<li>worked on 6th floor west and 8 south sprinkler heads.</li>
<li>worked on 8th floor south GRDs, box 8-1 install,</li>
<li>exhaust damper install in womens and mens room on 2ndfloor,</li>
<li>duct patching on 3 east.</li>
<li>9th floor east HVAC controls,</li>
<li>worked on duct replacement to box 9-27, 8-12,</li>
<li>duct for fire damper on 9th floor</li>
<li>Cleaning employees worked on dust and clean throughout building and final clean of 6 and 7 west.</li>
<li>worked on lights on 6 south west,</li>
<li>3 south wall trim out, lighting on 7 south, power through lobbies on 8 &amp; 9 for new damper install,V.A.V. disconnects on 9, rough in tie back walls,</li>
<li>worked on ceiling demo on second floor lobby,</li>
<li>8th floor east ceiling demo.</li>
<li>9th floor south final coats and touch ups, 3rd floor south</li>
</ul>
<img src="http://feeds.feedburner.com/~r/ChavezModernization/~4/kGapiAR6yjA" height="1" width="1"/>]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/11/friday-may-11-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		<feedburner:origLink>http://www.chavezmodernization.com/2012/05/11/friday-may-11-project-update/?utm_source=rss&amp;utm_medium=rss&amp;utm_campaign=friday-may-11-project-update</feedburner:origLink></item>
		<item>
		<title>Thursday May 10 Project Update</title>
		<link>http://feedproxy.google.com/~r/ChavezModernization/~3/33mtb7M62m0/</link>
		<comments>http://www.chavezmodernization.com/2012/05/10/thursday-may-10-project-update/#comments</comments>
		<pubDate>Thu, 10 May 2012 13:46:10 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=842</guid>
		<description><![CDATA[2 of 14,846 Thursday May 10 Project Update Jennifer Beck (8PSD) 7:37 AM (3 minutes ago) Reply to bcc: &#38;R08, bcc: Chavez Today&#8217;s Vendor: Mary Kay Where: 4th floor Vending area Time; 11:00 am to 2:00 pm Building Heating and &#8230; <a href="http://www.chavezmodernization.com/2012/05/10/thursday-may-10-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p>2 of 14,846</p>
<p>Thursday May 10 Project Update</p>
<p>Jennifer Beck (8PSD)</p>
<p>7:37 AM (3 minutes ago)</p>
<p>Reply</p>
<p>to bcc: &amp;R08, bcc: Chavez</p>
<p>Today&#8217;s Vendor:</p>
<p>Mary Kay</p>
<p>Where: 4th floor Vending area</p>
<p>Time; 11:00 am to 2:00 pm</p>
<p><strong>Building Heating and Cooling system Outage:</strong></p>
<ul>
<li>When: 6:00 pm May 11 through 10:00 am May 13</li>
<li>What: Building Air Supply. So no cooling, heating, or recirculated air.</li>
<li>Items Not affected: IT Server Rooms and electrical</li>
</ul>
<p><strong>Electrical Outage: Floor 6, 7 and 8 Only</strong></p>
<ul>
<li>Estimated for June 2: 8:00 am to 5:00 pm</li>
<li>Why: Installation of new HVAC units for zoning</li>
</ul>
<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>worked on removing and replacing door to women’s restroom during damper work to protect the door,</li>
<li>walked pre-punch list on 8th floor above ceiling and worked on demo of old above ceiling wall track,</li>
<li>walked pre-punch on 3 south arch, 9 south arch, 7 west arch, 6 west arch. </li>
<li>worked on dropping ceiling tile on 9 west,</li>
<li>grid on 6 south,</li>
<li>dropped tile in 785 secure room,</li>
<li>tape and finish on first floor for painter to start,</li>
<li>9 east sanding (ready for prime and first coats),</li>
<li>tie back drywall on 7 east,</li>
<li>demo in restrooms for dampers,</li>
<li>patched through wall holes above ceiling from duct removal on 8 west conference rooms,</li>
<li>fixed grid in 8 west conference room,</li>
<li>dry wall on 6 east ready,</li>
<li>worked on 8th floor west and south heads,  </li>
<li>worked on damper install on 2 mens rest room,</li>
<li>tie in return damper on 2nd floor,</li>
<li>VAV install 9-27,9-28,9-29, grds and slots on 8 west, 6 west and 7 west,</li>
<li>worked on V.A.V. controls on 6, controls at 8-15,  </li>
<li>worked on duct replacement and insulation at boxes 9-3, 9-7,</li>
<li>measured and duct install to boxes 9-27,28,29.</li>
<li>worked on dust and clean throughout building.</li>
<li>worked on reconfiguring lights on 9 west and south,</li>
<li>disconnect install on 9 FPVAVs, reconnect power to box 8-15,</li>
<li> lights install on 7 south,</li>
<li>F.A. rough in 6 south,</li>
<li>above ceiling pre-punch on 8 west.</li>
<li>remove all old ceiling supports and anchors in 8 west ceiling,</li>
<li>carpet demo on 7 south west for Décor.</li>
<li>worked on final coats on 6th floor west, 7th floor west, 3rd floor s.west, 9 south 7,6 west, 3 south, 9 south.</li>
<li>worked on carpet install on 7 south, pre-punch on 9 south.</li>
<li>worked on stool sill touch ups on 6 and 7 west. Almost done on west.</li>
</ul>
<img src="http://feeds.feedburner.com/~r/ChavezModernization/~4/33mtb7M62m0" height="1" width="1"/>]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/10/thursday-may-10-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		<feedburner:origLink>http://www.chavezmodernization.com/2012/05/10/thursday-may-10-project-update/?utm_source=rss&amp;utm_medium=rss&amp;utm_campaign=thursday-may-10-project-update</feedburner:origLink></item>
		<item>
		<title>Wednesday May 9 Project Update</title>
		<link>http://feedproxy.google.com/~r/ChavezModernization/~3/FSxhylxb7A8/</link>
		<comments>http://www.chavezmodernization.com/2012/05/09/wednesday-may-9-project-update/#comments</comments>
		<pubDate>Wed, 09 May 2012 15:13:19 +0000</pubDate>
		<dc:creator>jbeck</dc:creator>
				<category><![CDATA[Events]]></category>

		<guid isPermaLink="false">http://www.chavezmodernization.com/?p=839</guid>
		<description><![CDATA[Fire Protection Flow Test in Garage: Cancelled. This work will be rescheduled: TBD  Ceiling Demolition · 8th Floor East: Week of May 9-10 · 6th Floor East: Week of May 14 · 7th Floor East: Revised Schedule coming soon.  Note: &#8230; <a href="http://www.chavezmodernization.com/2012/05/09/wednesday-may-9-project-update/">Continue reading <span class="meta-nav">&#8594;</span></a>]]></description>
			<content:encoded><![CDATA[<p><strong>Fire Protection Flow Test in Garage:</strong> Cancelled. This work will be rescheduled: TBD</p>
<p> <strong>Ceiling Demolition</strong></p>
<p>· 8th Floor East: Week of May 9-10</p>
<p>· 6th Floor East: Week of May 14</p>
<p>· 7th Floor East: Revised Schedule coming soon.</p>
<p> Note: Ceiling tile will be coming soon!! Starting on West, South, East and then North.</p>
<p> <strong>Tenant Move schedule:</strong></p>
<p>· 7th and 6th Floor West: Office Shifts May 10 at 6:00 pm.</p>
<p>· Tenant Move: May 14 at 6:00 am.</p>
<p>· 3rd Floor West and South: May 18th at 6:00 am.</p>
<p>· 9th Floor South: May 23rd at 6:00 am.</p>
<p>· 8th Floor South: June 1st at 6:00 am.</p>
<p><strong>Exterior:</strong></p>
<p>· New grass and trees will be coming soon to the garage landscaping.</p>
<p><strong>Schedule:</strong></p>
<p>4 week look-a-head: <a class="downloadlink" href="http://www.chavezmodernization.com/wp-content/plugins/download-monitor/download.php?id=129" title=" downloaded 20 times" >Week of May 7 Schedule (20)</a></p>
<p>Tenant Relocation Schedule: <a class="downloadlink" href="http://www.chavezmodernization.com/wp-content/plugins/download-monitor/download.php?id=130" title=" downloaded 16 times" >Tenant Relocation Schedule (16)</a> </p>
<p><strong>Update of Construction from Last Night:</strong></p>
<ul>
<li>Tile got dropped on the north half of the west side of 9.</li>
<li>Secure room 785 is inspected and ready for ceiling tile to drop Wednesday night at 5:00 P.M.</li>
<li>worked on replacing railing in 7thfloor hearing room,</li>
<li>walked pre-punch on 6 and 7 west, 9,3 south,</li>
<li>worked on dropping ceiling tile on 9 west,</li>
<li>grid on 6 south,</li>
<li>tape and finish 9th floor cubicle wall,</li>
<li>tape and finish 6 south,</li>
<li>Tape and finish 9 east,</li>
<li>tape and finish touch up on 3 east and 3 south,</li>
<li>Tie back walls on 7 east, 8 east.</li>
<li>worked on 7th floor north west heads, secure room 785 heads.</li>
<li>V.A.V. install 8-15,</li>
<li>GRDS on 6 west and south.</li>
<li>worked on fixing temperature controls for box 9-14,</li>
<li>6th floor FPVAV controls in south west corner existing box,</li>
<li>worked on duct demo and reinstall at boxes 9-5, 9-6, 9-26 rezone,</li>
<li>insulated duct in 9 south east.</li>
<li>worked on dust and clean throughout building.</li>
<li>worked on lights on 7 south,</li>
<li>data cable re-route on 9 east conference room, lights in secure room 785,</li>
<li>worked on ceiling demo on first floor lobby</li>
<li>worked on final coats on 6th floor west, 7th floor west, 3rd floor s.west, 9 west at Curtis cubicle, walked pre punch on 7,6 west, 3 south, 9 south.</li>
<li>worked on carpet install on 3 east, carpet removal in 7 hearing room, pre-punch on 6,7, west, 3 south, 9 south.</li>
<li>worked on stool sill install on 6 east, 6th floor west and 7th floor west sill touch up.</li>
</ul>
<img src="http://feeds.feedburner.com/~r/ChavezModernization/~4/FSxhylxb7A8" height="1" width="1"/>]]></content:encoded>
			<wfw:commentRss>http://www.chavezmodernization.com/2012/05/09/wednesday-may-9-project-update/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		<feedburner:origLink>http://www.chavezmodernization.com/2012/05/09/wednesday-may-9-project-update/?utm_source=rss&amp;utm_medium=rss&amp;utm_campaign=wednesday-may-9-project-update</feedburner:origLink></item>